The Village received notice on
Friday 7/17/2020 from FEMA regarding the outstanding appeals on Hurricane Irma denied
claims.
Before I get into that language,
we need to backtrack a moment and follow the timeline due to the devil is in
the details.
The amount the Village submitted to FEMA for reimbursement
was $1,077,470.70 with the amount denied=
$748,567.66. The 3 part work order breakdown
is as follows:
1)
Grants Manager Project (GMP) 5511= $28,140.75
2)
GMP 5517= $540,335.00
3)
GMP 12857= $180,091.91
Total $748,567.66
The initial
response from FEMA in their letters dated 2/13/2019 - 2/22/2019 stated: “"FEMA determines that the procurement contract and documentation for
Grubbs and BCPeabody (debris monitoring) for the Village of Biscayne Park violates
Federal law, regulations and policy in multiple ways. “
1) Regarding the Grubbs
"piggyback" contract: "The
contract was a contract onto an existing contract between Hernando County, FL.
and Grubbs. In the case of Hernando County, no such documentation was provided
beyond that showing Grubbs as the selectee. A FEMA procurement checklist for
the County debris contractors indicates "no respondents were
rejected" further indicating Grubbs was the only respondent to the
solicitation." Therefore, the County and the Village failed to
substantiate the original contract was competitively procured.”
2) Regarding the monitoring contract: “The original BCPeabody contract was not properly procured, and the
contracts omitted provisions required by Federal standards, the Village did not comply with Federal regulations for use of
existing contracts and the adequate documentation was not provided."
Due to that the Villages reimbursement submittal
“violated Federal law, regulations and
policy in multiple ways” the previous Village attorney (Rebecca Rodriguez) was
tasked to file appeals on April 2019. The gist of the explanation she gave was (paraphrased
from memory) “we believe we were correct, but if not, you should reconsider payment
due to the high amount of Hurricane activity that year, etc.”
OK… seems superficial to me, but let’s move
on.
Also, “in
support of its appeal, the Subrecipient (Village) provided additional
procurement documentation,” which included the complete Grubbs contract from
Hernando County, FL. demonstrating that the original contract holder procured
the contract competitively.” (By the way, the Grubbs contract was in the
Village’s possession… but not originally submitted) So, this is a mistake that
was corrected… but at a cost to taxpayers by way of the appeal.
Based on the Project Status Report, the initial
obligated amount for reimbursement was $115,269.98 with another $234,650.83 in
the queue for possible payment “pending tipping fee receipts.” This amount equals $349,920.81 total. There were no other entries. However, in order to secure this money in the queue, the
tipping fees needed to be produced and presented to FEMA. Important point: Neither H20 Partners nor BCPeabody had them. These
receipts were not included in the appeals or during the first submittal by
the Village.
It was David Hernandez who finally tracked
them down on or about July 5th 2020. He realized through his investigation
that there was no contract with Waste Management, but did find money paid out to
Waste Management. He then followed the money trail to discover and secure the tipping
fee receipts that were then submitting for consideration.
That was the missing key towards our further reimbursement.
Once again, as some here aren’t clear on the
timeline, Tracy, Krishan or the previous law firm had absolutely nothing to do with
these tipping fee receipts as they were discovered after they were all gone, terminated or otherwise out of the
picture. The same can be same for the current Commission. All of this was being
dealt with by the Manager alone.
Now, in closing the letter from FEMA on Friday
stated that the obligated reimbursement is $666,259.76 (to include the $234,650.83 in the queue). The adjusted work order breakdown is as follows:
1)
Grants Manager Project (GMP) 5511= $28,140.75
2)
GMP 5517= $524,678.75
3)
GMP 12857= $113,440.26
Total $666,259.76
However; I am still unclear on 2 points:
1) Their denial letter from
2/13/2019 clearly stated that the original BCPeabody contract was not properly
procured, and the contract omitted provisions required by Federal standards, Federal
law, regulations and policy in multiple ways. Meaning that FEMA then did not find
the reason/excuse given for non-competitive bidding was valid.
In the FEMA letter from 7/17/2020, it appears
they have now changed their previous position- although deducting -$15,656.25
for what I can conclude were time delays. “Debris
monitoring services were properly procured.” Their reasoning, “debris removal necessary to protect the
lives, safety and health of the general public would have been delayed if the
Subrecipient meets the requirements for noncompetitive procurement of debris
monitoring services,” So, this additional mistake is now being overlooked
as other cities also had issues with the monitoring procedures. But, let’s not
look a gift horse in the mouth… I’m happy to report we got a far better outcome
than I expected. We got lucky on this one.
2) The difference between the current
reimbursement of $666,259.76 and the previous anticipated amount of $349,920.81
remains unclear to me. As mentioned above, there were no other payment amount entries listed in the queue. I can only assume that the tipping fee receipts also
helped towards the higher amount. Perhaps not, and I will edit this post if and
when more information becomes available on this point.
So, this hopefully concludes our Hurricane
Irma experience and explanation.
This was a horribly mismanaged operation, top
to bottom that we have somehow now fiscally survived. The lesson learned should
be we can never again enter into Hurricane season as unprepared as we were then.
But, that’s not the only point; the point is also
to give credit where credit is due- setting politics aside.
And the credit for this more than expected favorable outcome goes to David Hernandez.
Standing Watch,
Milton Hunter
The Biscayne Parker
Hi Milt,
ReplyDeleteWhat happened to the orig 329K that was not denied? It looks like the village never applied for it. Is the village getting the 666k plus the 115k already received?
As far as I can tell Gray Robinson had already been paid the contracted amount of 15k.
Did GR and the Village only appeal the 349 and not the 748 plus the 329k?
Hi Harvey,
DeleteThere are still lingering questions as to what they will pay vs. the denial letter originally. Clearly, changes were made afterwards. My belief is that the total is the $666K number that includes the previous payment received. If and when I can figure the rest out, I'll be sure to update this post.
Stay safe-
Looking a little closer at the numbers...I'll make an assumption as to the difference between the work orders from last years denial to the more current FEMA obligation.
ReplyDeleteGMP 5511 (initial push to clear streets)= $28,140.75- same on both, unchanged
GMP 5517 (actual hauling and work fees)= $540,335.00/ $-15,656.25- -2.9%
GMP 12857 (monitoring fees)= $180,091.91/ $-66,651.65- -37%
These were the 3 components of the claim. Overall amount difference/adjustments between to two= $-82,307.91- -11%.