Don’t Shoot the Messenger! The
messenger is NOT the problem… The Problem is The Problem.
Last night there was a Special Commission meeting to discuss
the budget overruns on the two building projects. This was requested by Commissioner
Anderson as the original item (regular April Commission meeting) was placed
near the end of the agenda and due to the late hour, few residents would have
been there to hear it. But, before we take a step forward… we must first take a
step back to understand the situation and problems that arose from what looks
to be a lack of fiscal oversight.
In advance of the April meeting (disclosed in the backup), it
was discovered that the alleged total for both buildings was $1,800,147.24. To
repeat, one million eight hundred thousand dollars! I use the word “alleged “due to the fact it appears that
there were project expenses (such as the landscaping for the log cabin and
others) that were not included in the reconciliation. Why? Beats me.
The data provided in the reconciliation statements is very confusing,
but regardless, the point remains the same. To that end Chuck Ross has
reconstructed the numbers for both projects and listed below is a brief overview.
First, adding back the
$89,000.00 fee for the architect (that somehow was missed in the manager’s feasibility study
to borrow the $350K loan- how does that happen?) and the adjusted contingencies, we started out the project underfunded
by $126,891.00 [7.64%] back in May, 2015. This was before we ever broke ground.
As to the cost overrun, Chuck is coming up with $161,216.00 or [8.85%] The funding shortage of $126,891.00
was the leading cause of the $161,216.00 overall shortage. There were
unexpected post construction credits and grants that reduced the shortage by
$34,600.00 to $126,616.00 - not the $115,213.24 [6%] as claimed by the manager
in her report.
However, as mentioned above, there are some costs yet to be identified.
To reflect a shortage of $115,123.24 net of the unexpected credits and
omitting certain costs is misleading. Clearly the planning
was suspect.
Two points to learn from this:
First, the manager should have recalculated the
funding requirements after the final bids for the Log Cabin project had
been accepted. The error (funding shortage) would likely have been discovered
and adjustments would have been made to the project.
Second, the manager did not report
to the Commission the change orders as the project progressed. Again, the
error would likely have been discovered.
Since the Commission was not made
aware of the additional costs, they did not have the opportunity to assess
changes that could or should be made to the project to take into account the
additional funds required to complete the project.
Total
expenditures Village Hall= $969,909.80
Total
expenditures Log Cabin= $830,237.44
Again, this is assuming that the reconciliation total costs
are complete and accurate. This number was a shocker as how many residents even knew about the budget for the two buildings? I know that Commissioner Ross had
been asking for progress reports and financial updates for many months only to be delayed by the
manager. It was never fully
disclosed to the public (taxpayers) until again, months after the fact.
And herein lays part of the problem. Where was the fiduciary responsibility from both the manager and our Commissioners
during the process? Why was there no degree of any fiscal restraint
when the budget overruns were first discovered? And who was responsible for signing off on all of this overage?
Section 4.07. - Appropriation
amendments during the fiscal year.
(B) If, at any time during the fiscal year, it appears probable to the
Manager that the revenues available will be insufficient to meet the amounts
appropriated, s/he shall report to the Commission in writing without delay,
indicating the estimated amount of the deficit, and his/her recommendations as
to the remedial action to be taken. The Commission shall then take such
action, as it deems appropriate, to
prevent any deficit spending not covered by adequate unappropriated financial
resources including reserves.
In short, this just didn’t happen. This wasn’t an
“option” but a Charter requirement. The manager did not publicly address the
budget overages, without delay, and instead ostensibly just made her own
decision to keep spending unappropriated Village funds. Nor was this Charter
requirement adhered to on another potential cost overrun of approx. 50% (over the
grant amount) towards the new Village Signage. (half of which, by the way, have
not been installed due to running out of money by the inclusion of solar lighting that somehow got added to the
project after the fact. Solar lighting within our dense tree canopy… was this a good idea?) Especially after
just running over budget on your prior project? Do
you see a trend here?
It seems as if our Commissioners bought into the paradigm of “not
micromanaging the manager” to the degree of simply providing no fiscal management or institutional oversight
at all! Or, in fairness, of potentially being rebuked by the manager if
efforts were indeed attempted citing “I’m
the professional here, don’t micromanage me,” etc. Further, there seems to
be some misunderstanding of what the term “micromanaging” means.
Definition
of micromanage
To try to control or manage all the
small parts of (something, such as an activity) in a way that is usually not
wanted or that causes problems
Definition
of oversight
Watchful and responsible care b: regulatory supervision
See the
difference? But for whatever the reason, blind
trust was offered and we now bear the cost for such lack of judgement. For me it's the process, poor planning, and the lack
of transparency of not informing everyone what these buildings were actually
costing us... until it was too late. The bottom line is always what is
this going to cost us – the Biscayne Park taxpayers.
We hired a first-time manager who had over the past
year demonstrated varying concerns regarding both her attitude and work
performance. These concerns were shared with our Mayor and other Commissioners,
yet were seemingly overlooked. Remarkably, some STILL seem to want to overlook these problems. Per her employment
agreement “The Village Commission agrees to annually review the performance of
the Village Manager prior to the anniversary date of this Contract.” This
should have been done prior to last October… yet it didn’t happen. Why?
In my opinion this is cause for concern moving
forward. Trust should be earned over a period of time based on deeds and
performance… not just given freely to any new Village employee.
I can only hope that we’ve learned a hard lesson
based on this experience as we now move on to our next manager. (Oh, and sorry
for burying the lead, for anyone who didn’t already know, our manager has
resigned effective April 29th.)
Which leads me to this:
Don’t
Shoot the Messenger! The messenger is NOT the problem… The Problem is The Problem.
Deal with it and shoulder the responsibility you chose when you sought public
office.
To suggest that our residents that pointed out legitimate
concerns about the manager were The Problem is in truth, well… insulting.
Insulting and delusional. Deflecting Problems does not solve The Problem. Pointing
out Problems does not create The Problem. Lack of action only further increases
The Problem. Our residents have every right to expect better results and
representation from our elected officials.
The manager will soon be gone, yet we remain to
pick up the pieces. It’s time for our leaders to lead.
Standing Watch-
Milton Hunter
The Biscayne
Parker
miltonhunter@gmail.com
P.S. The videos of the April meetings are now up on YouTube.
Links below:
April 5th Regular Commission meeting- https://www.youtube.com/watch?v=RJirEBdFl_s
April 11th Special Meeting/ manager resignation- https://www.youtube.com/watch?v=THWhaF-ymPk
April 20th Special Meeting- Buildings budget
recap- https://www.youtube.com/watch?v=FJAq-Js2YmI
One thing you didn't mention in your breakdown was the total amount of grant money we received. The total project cost, as reported by the manager was $1,800.147, and the total grant money was $1,075000. That leaves $725,000, the village had to cover. As you mentioned we took out a loan for $350,000, so the village had to take $375,000 from the general fund or the revenue account. That's a lot for us to absorb even over a few years. If there was better oversight and planning we could have been given the option to take a larger loan and spread it out over 10 years. Instead of putting all of that money into the buildings we could have used some of it to repair our roads, improve our medians and lighting and even lower our taxes.
ReplyDeleteHi Barbara,
DeleteYou make many good points and yes, there is quite a bit I didn't mention. Firstly, due to the fact that I feel we haven't accounted for ALL of the spending on these projects. It's all very confusing to try to reconstruct.
Big thanks to Chuck for his assistance in providing some clarity to this situation. We'll update as more information becomes available. Stay tuned.
Best,
Milt
Barbara,
DeleteIt's less than $375K because $75K was obtained from selling the old sanitation trucks. Also, remember that we could have moved the Police to the PW building and there was a potential savings of approx. $150K, but numerous residents objected to that.
To me, if the village sells their sanitation trucks for 75K then that money should revert back to the general funds or revenue fund. They were our property and we just converted them into cash. The 75K could have been used to buy a new truck for public works or a million other things. That shouldn't be considered as some free money that we got. The grant money was money from someone else. The truck money was our money.
DeleteChuck - as far moving the police to PW please don't blame only the residents. Several commission members including Bob and the Police Chief objected to that move. Bob felt that the retrofitting of the PW building would have used up the majority of the savings. I did not agree with him. Personally I would have liked to see the numbers. Too bad we didn't have all the necessary information in time to make better decisions.
ReplyDeleteJaney,
ReplyDeleteI'm not blaming anyone, but merely pointing out that there was a possible savings and the general consensus or priority was to not save money first but to do what was perceived as the best possible fit for the Village. That consensus was to place the Police at Village Hall. So that was placed higher than possible savings, so be it. I'm fine with the result.
Barbara,
Yes, you are correct the trucks were assets of the Village and could have been turned into cash and placed as reserves. That was not the point. The point was those assets were utilized to fund the project. The building is also an asset of the Village, and in my opinion enhances the Village more than having those funds in the bank. So we traded old vehicles for helping fund a new or renovated building that will last for many decades.
My point was not to argue if we should have used those funds from the truck sale. My point was if you're giving an account of how mow much the village had to come up with, then it's 375K.
DeleteAll,
DeleteI too agree that we should have invested more time and consideration into the annex building spending. In hindsight (which, of course is always 20/20) we spent too much money on that one project.... nearly the entire one million dollar grant!
I would have liked for this decision to have been a financial one instead of any other reasoning based on a perceived best fit. Moving the police into our underused (existing asset) PW building would have had its pros and cons. Like everything else. But it would have saved the Village, if I remember approx. $150,000.00.
Almost the entire cost overage...
Barbara,
DeleteMy comment was not to argue but to point out that we traded one type of asset for another type of asset. It's another way to look at it.
This comment has been removed by a blog administrator.
ReplyDeleteGood to hear from you... it's been a while. There certainty were bumps along the road to completion... that's for sure. Some that should have been avoidable. That's the kicker here.
DeleteAlso, I think the mural decision was made by our prior Commission. For what it's worth.
H,
DeleteOof, I deleted your comment in error. I was attempting to change my reply to you. Sorry about that. Here is your re-port:
Thanks for shedding light and clarity on this Milton!!! It is clear this commission has been asleep at the wheel. The lack of business sense exhibited by our elected and paid officials is shameful.
I think back to the ridiculous handling of the mural at the park where they released their budget when asking for proposals. The fact that they could effectively manage a $5000 bid was probably the canary in the mine that should have let us all know they couldn't handle a project of this magnitude. At least the manager resigned...
Milt re: the mural - you are correct. It was the prior commission. I don't recall whether the RFP was seen by the entire commission prior to publishing but I do recall almost unanimous objections by the public - not so much against the idea of a mural but against public funding. And the questions about putting a $$ amount in the RFP also fell on deaf ears.
DeleteJaney,
DeletePerhaps this is why there is a perception from some that the Commission doesn't listen to the public...taxpayer. Of course, this example was not from our current group, but the dais example could be.
Was that really the best use of our money (approx.$24K)for the "public?" I mean, how is the public benefiting from it.
One more example, how many street lights could we had installed on dark street with that $24K? Better street lighting could have a potential effect on crime as well as our overall property values...
Even assuming some monies would have been needed for some type of "dais" surely it could have been done for far less than $24,000 leaving the remaining monies for something that actually benefits the residents. Another example of the majority of commission members not listening to the public.....the $5000 that 3 of them agreed to give out in bonuses to employees for taking on some additional work while the manager position is open. The public spoke against it, reminding them that taking on additional work when someone leaves is the norm in any organization - and you don't get additional pay - it's just what you do as part of a team. And at least a couple of the employees who will get this extra money haven't even been here a year. Now granted, a bonus is better than the original idea of a raise but it still does nothing for the public. If there is a spare $5000 (although how could there be with $115,000 to cover??) it could have gone back into the landscaping budget which had monies removed to cover the landscaping at village hall.
DeleteMorning Janey,
DeleteRemember according to Chuck the number is not $115K. That number was a misrepresentation. It's higher than that. And as it will take more time to figure the true total out, I'm not sure how anyone can expect any extra spending. You can't write checks when you don't know your balance, can you? This is just the reality of the situation for now as I see it.
At Wednesday's meeting we were told all the bills have been paid. What I don't recall hearing is where specifically (what line items in this current budget)was the money drawn from to cover the $115,000+ overage.
ReplyDeleteFrom Linda Dillon:
ReplyDeleteWhile everyone seems to have slightly different viewpoints regarding the two projects, I hope we can all agree that the end products are two beautiful buildings that should outlast most of us. For me, at this point, what’s done is done. I just hope there are lessons learned and that additional steps are put into play to ensure that this type of situation never happens again and that there is improved communication at every level within our Village so that we can all enjoy the wonderful things our community has to offer. Sounds a bit kumbaya-ish, doesn’t it.
At the same time, contrary to what our Mayor and perhaps at least one of our Commissioners might like, I hope anyone who has a concern will continue to speak up without being labeled as someone who has “overstepped the boundaries” or one who is trying to “micro-manage”.
We must always remember the words of poet John Lydgate who said, “You can please some of the people all of the time, you can please all of the people some of the time, but you can’t please all of the people all of the time”. Margareat McBride added to these words and said, “You can please some of the people all of the time; all of the people some of the time and some of the people NONE of the time, and these are the people you PRAY for ALL of the time.”
Amen,
Linda
Words of wisdom Linda... thanks for sharing.
DeleteWe need a "like" button on this blog! Well said Linda!
ReplyDeleteJaney,
DeleteAgreed. I'll check to see if there is an option ;-)>
Somehow, I think Biscayne Park needs a "quality assurance" department. The kind that reports at every meeting what is happening in BP both good and bad, the kind of quality assurance department that is not just for show, but can illuminate everything both to the commission, managers and public. This kind of QA can motivate and push for improvements on a ongoing and continuous basis. I used to work QA "Demings" style. It is sorely needed here. Thanks
ReplyDeleteHi Elona,
DeleteYou and I share a belief that government should be run more like a business. And while I see certain advantages, I have been reminded by others that this is just not always the case.
However, proper oversight of our employees with a nod to fiscal responsibility should not be exclusive to business. It's needed everywhere. And at least several of our Commissioner's have pledged to do so moving forward. And that's a step in the right direction, IMO.